High School #2

Project at a Glance
- Location: Off Reimers-Peacock Road near State Highway 71 in western Travis County
-
Capacity: Designed for 1,500 students with athletics facilities included; flexibility to expand to 2,000 students in the future
-
Timeline:
-
Roadway Improvements
-
Start - Spring 2025
-
Estimated Completion - Fall 2026
-
-
New School Construction
-
Start - TBD (permit acquisition in progress)
-
-
-
Board Actions:
-
March 2025: $11.88 million contract awarded to Liberty Civil Construction for roadway improvements
-
March 2025: American Constructors selected as Construction Manager at Risk (CMR)
-
September 2025: Guaranteed Maximum Price (GMP) of $46.36 million approved for Phase 1 construction
-
-
Community Engagement: Lake Travis ISD has completed a community engagement process to gather input on the name and school colors for High School No. 2. The process followed Board Policy CW (Local), which establishes criteria for facility naming based on local residential or geographic areas, landmarks, and historical significance.
Community members were invited to submit suggestions through an online Google Form posted on the district’s website. The form was promoted through direct email to parents and staff; district and campus newsletters; electronic flyers; and district social media platforms. The form was available from December 3, 2025, through January 12, 2026.
More than 1,900 responses were received. The district appreciates the community’s engagement and thoughtful input throughout this process.
The Board is scheduled to consider approval of the school name and colors at its regular meeting on February 18, 2026.